Summer Palms Faridabad

Construction in full swing. Appended Tower-wise status as on 28th September 2011:

  • Tower A1 - Slab Casting - Complete, Brick Work - Complete upto 11th Floor, Internal Plaster - Complete up to 6th Floor
  • Tower A2 - Slab Casting - Complete upto 10th Floor, Brick Work - Complete upto 6th Floor
  • Tower B1 - Slab Casting - Complete, Brick Work - 12th Floor in Progress, Internal Plaster - Complete up to 6th Floor
  • Tower B2 - Slab Casting - Complete, Brick Work - Complete , Internal Plaster - Complete up to 10th Floor
  • Tower C1 - Slab Casting - Complete, Brick Work - Complete , Internal Plaster - Complete up to 9th Floor
  • Tower C2 -  Slab Casting - Complete, Brick Work - Complete , Internal Plaster - Complete
  • Tower D1 - Slab Casting - Complete, Brick Work - 13th Floor in Progress, Internal Plaster - Complete up to 12th Floor
  • Tower D2 - Slab Casting - Complete, Brick Work - Complete , Internal Plaster - Complete