Summer Palms Faridabad
Construction in full swing. Appended Tower-wise status as on 28th September 2011:
- Tower A1 - Slab Casting - Complete, Brick Work - Complete upto 11th Floor, Internal Plaster - Complete up to 6th Floor
- Tower A2 - Slab Casting - Complete upto 10th Floor, Brick Work - Complete upto 6th Floor
- Tower B1 - Slab Casting - Complete, Brick Work - 12th Floor in Progress, Internal Plaster - Complete up to 6th Floor
- Tower B2 - Slab Casting - Complete, Brick Work - Complete , Internal Plaster - Complete up to 10th Floor
- Tower C1 - Slab Casting - Complete, Brick Work - Complete , Internal Plaster - Complete up to 9th Floor
- Tower C2 - Slab Casting - Complete, Brick Work - Complete , Internal Plaster - Complete
- Tower D1 - Slab Casting - Complete, Brick Work - 13th Floor in Progress, Internal Plaster - Complete up to 12th Floor
- Tower D2 - Slab Casting - Complete, Brick Work - Complete , Internal Plaster - Complete