Monsoon Breeze , Sector 78 Gurgaon
Construction in full swing. Appended Tower-wise status as on 20th October 2011:
- Tower C - 12th Floor Complete, Brick Work - 12th Floor Complete
Tower D - 12th Floor Complete, Brick Work Complete, Inter Plaster - 12th Floor in Progress
Tower E - 11th Floor Complete
Tower F - Penthouse Complete, Brick Work Complete, Internal Plaster - 10th Floor Complete
Tower G - Penthouse Complete, Brick Work Complete, Internal Plaster - 11th Floor in Progress
Tower H - 12th Floor Complete, Brick Work Complete, Internal Plaster Complete, External Plaster Complete
Tower I - 12th Floor Complete, Brick Work -12th Floor in Progress, Internal Plaster - 8th Floor in Progress
Tower J - 12th Floor Complete, Brick Work Complete, Internal Plaster - 11th Floor in Progress
Tower K - 12th Floor Complete, Brick Work Complete, Internal Plaster Complete